News Flash

Home

Posted on: August 16, 2021

City Construction Projects

Construction updates for the week of July 24

RDIIA – Conveyance Sewer along 7th St & Ramsdell St

Past week

  • Connected water services and sanitary laterals to the new water and sewer mains on Ramsdell Street between 7th and 6th Streets
  • Connected new watermain in the intersection of 7th and Ramsdell Streets
  • Graded Ramsdell Street road subbase to final elevation on from 7th to 6th Street

 Upcoming week

  • Place aggregate base course on Ramsdell Street from 7th to 6th Street
  • Construct temporary watermain on Ramsdell from 6th to 5th Street
  • Mill existing asphalt on Ramsdell Street from 6th to 5th Street

 

RDIIB – Treatment Facility

This past week

  • Completed installation of overflow pump drives
  • Continued screening and spreading topsoil to final grade through-out site
  • Worked on Grit equipment controls
  • Worked on Raw sewage pumps

 Upcoming week 

  • Complete a system trial run
  • Punchlist items

 

2022 12th Street Improvements

This past week

  • Finished grading subbase and crushed asphalt aggregate base for curb and gutter
  • Sawcut road at POB and POE
  • Placed concrete pedestals for Rapid Rectangular Flashing Beacons
  • Started grading north sidewalk sand base

 Upcoming week

  • Pour concrete curb & gutter, radii, drive approaches, sidewalks
  • Finish grading north sidewalk sand base

 

2022 Street Improvements - Quincy & Cleveland 

This past week

  • No work this week

 Upcoming week

  • Contractor waiting for back ordered materials to begin construction
  • Tentative start at end of July or early August

 

2022 Memorial Drive Reconstruction 

This past week

  • Installed traffic control
  • Mobilized equipment to jobsite

 Upcoming week

  • Begin demolition and removals

 

DWAM Grant Hydro-Excavation

This past week

  • Hydro-excavated water services along US-31 corridor

 Upcoming week 

  • Complete additional hydro-excavating water services
  • Final restoration

 

Water Tower Improvements

This past week

  • Completed painting Industrial Water Tower
  • Started locating where City Logo will be on the tower

 Upcoming week

  • Complete painting of City Logo on the Industrial Water tower

 

Riverbank Damage Bank Erosion

Upcoming week

  • Monitoring vegetation growth


Facebook Twitter Email