Construction updates for the week of June 4
2023 Street Improvements - S. Lakeshore Drive
This Past week
- Split rail fencing installed alongside the north side of Rotary park at 1st Street
- Additional signage installed along corridor
- Conducted final site walkthrough to determine punch list items for the contractor
Upcoming weeks
- City DPW to be ordering and installing additional “Do Not Enter” Sign at the exit of the Lions Pavilion parking lot
- Contractor working on scheduling punch list items
- Contractor working on scheduling 2nd application of pavement markings
- Waiting for delivery of new street lights
Cleveland Street (US-31) Sanitary Sewer Rehabilitation
Upcoming weeks
- Contractor mobilizing to the site to begin cleaning, dye testing for lateral verification, and televising sanitary sewer main to order materials for rehabilitation of the deficient sanitary sewer
S. Lakeshore Drive Water Main
This Past week
Upcoming weeks
- Working with directional drilling contractor to schedule construction of new water main loop from Douglas Park Dog-park to Harbor Drive